News from Arena Nanterre 92

Monday, 01 February 2016

The shipping of steel structure is compleeted.

 2016.03.18

With the truck n. 60 of 29th of january 2016 ended the provision of structures related to the « south mega beam » of Arena Nanterre 92, built by LMV to Vinci Construction and shipped in Paris.

Here are some numbers of the work order:

- 1.100 tons shipped with 60 trucks including 4 special transports;
- More than 10.000 m ² painted;
- 9.860 pieces manufactured and shipped.

Nicola Zanin

Project Manager

LMV S.p.A.