Last few hundred meters of a monorail were installed at the final stage of construction works for People Mover project. The first tests of Marconi express trains were conducted for checking the system in the section between the G. Marconi Airport station and Lazzaretto station. Photos from the site are below.
LMV Group performed executive design, working documentation and shop drawings for steel structures, production, installation of main steel elements and auxiliary works (construction of viaducts, stations, emergency stairs etc).